| Yes, HVAC unit heat strips may be changed in the field, as long as the HVAC unit
and heat strip package are UL listed to do so, and appropriate procedures are
followed. Occasionally large projects run into problems, such as building
electrical requirements exceeding the power available at the site, or an
original bid including an undersized main distribution panel, or undersized
site switch gear.
One of the first places planners look to solve these problems is the HVAC
system, especially if the HVAC units include heat strips for primary or
secondary heating. Let's look at why, and some possible solutions; first, some
background on heat strip testing per UL listing standard, then what options are
available to change heat strips in the field.
If HVAC equipment manufacturers had a choice, they would eliminate heat strips
from HVAC units altogether because of the extensive test procedures involved
with the process.
Heat strip testing involves monitoring hundreds of thermocouples during normal
and abnormal operating modes to ensure that excessive duct or unit temperatures
are not created. This testing must meet or exceed current UL requirements.
HVAC equipment manufacturers submit to UL the different sizes (KW) of heat
strips for use in their units. This could be literally any size, but usually
nominal increments of 5 KW (5, 10, 15, 20) are selected in single and three
phase. Next the HVAC equipment manufacturer decides to submit the heat strip
package to UL as a factory-built-in package only, a field-installed package
only, or a factory/field-installed heat strip package.
If the HVAC equipment manufacturer has submitted their units to UL for
factory/field installation, you are allowed to select and change in the field
the heat strip package to larger KW (more amperage) for more heat, or smaller
KW (less amperage) for less heat. However you must use the heat strip package
as provided by the HVAC equipment manufacturer and as listed by UL. Otherwise
adding, removing, or modifying heat strip package wires, parts, or the heat
strip itself violates the UL listing and has tremendous liability associated
with it.
Increasing a heat strip package KW will require a larger circuit breaker and
wire size. Reducing the heat strip package KW does not necessarily require a
change to smaller wire, but will require a properly sized (smaller) circuit
breaker. Electrical inspectors are required to follow the circuit breaker and
wire size listed on the data/serial plate for switch gear sizing.
|
At no time should anyone ever clip, or disconnect the wires on a heat strip to
disable half or a portion of it's capacity. |
| |
|
| 1. |
This violates the UL listing. |
| 2. |
Liability for fires and electrocution falls on those who
cut/disconnected the heat strip. |
| 3. |
Required review and change out of the heater limit or TCO
switch, a Serious Risk Issue. |
| 4. |
Limit control protection varies depending on what was
cut/disabled, a Serious Risk Issue. |
HVAC equipment manufacturers with factory-only heater packages put data/serial
plates on their units, which clearly identify the heat strip KW size, wire
size, and amperage. Only a few HVAC units with a factory-only installed heater
package have the option of a single point field wiring kit. Most HVAC units
with a field-only installed heater package require two field circuits: one for
the unit, one for the heater package. Very few equipment manufacturers have a
single point wiring kit for field installed heater packages. Two field wiring
circuits is the norm.
HVAC equipment manufacturers with a factory/field installed heater package must
also provide a means of marking the unit data/serial plate to comply with the
UL listing. It is important that the data/serial plate be properly changed
according to the manufacturers installation instructions and UL listing.
So yes, HVAC unit heat strips may be changed in the field, as long as the HVAC
unit and heat strip package are UL listed to do so, and appropriate procedures
are followed.
Which now brings us back to the challenges faced on projects with the building
electrical load exceeding what the end user has on site, and how this relates
to the HVAC equipment. We have seen how the use of heat strips impacts the KW
and wire size. A look at amperage is important also for electrical load
planning.
During the initial discussion with the End User, the dealer should ask how much
amperage is available at the site, or estimate for the end user what the
requirement may be. All too often on complex projects, the End User and/or
Dealer do not obtain this information soon enough to prevent site problems or
costly project redesigning. Having some basic information up front about
building electrical loads is critical.
Rules of thumb for 3 ton single
phase units per 12 x 60 module: |
| Gas/Elec Unit 30 amp per floor |
| A/C with 10 kw 60 amp per floor |
| A/C with 15 kw 90 amp per floor |
| HP with 5 kw 60 amp per floor |
| HP with 10 kw 90 amp per floor |
Simply multiply the number of modules times the selected HVAC unit above to get
an idea of the total building HVAC load. If the building is zoned and larger
units are used, the total could be less, but that takes further review of the
project to determine. Then add in the requirement of all other electrical loads
such as lighting, water heaters, receptacles, etc.
To avoid facing the major problem of "too much building, not enough power", and
the associated concern of "illegal" removal, cutting, or disconnecting heater
packages later on, simply pre-calculate the electrical load for the project.
Many building manufacturers will pre-calculate the electrical load for the
Dealer/End User when some basic information is available to determine HVAC unit
size on a project.
Contact your building manufacturer, mechanical engineer, or equipment supplier
with the size of the site amperage available at the beginning of your next
project. Your review of the electrical load of the project up front will save
time and money for all involved. If you find that you have electrical loads on
site greater than the switch gear or amperage available, remember to refer to
the manufacturers installation instructions and UL listing to avoid costly risk
and liability.
Stay fully powered until the next time we meet in . . . The Comfort Zone.
|